jmeter ramup设置_性能测试期间如何在jmeter中执行并发10000K线程?
Is that possible to execute 10000 concurrent user in jmeter?If so how?What should be the ram-up time for this scenario??解决方案JMeter's limit of virtual users per Thread Group is very high, to be precise
Is that possible to execute 10000 concurrent user in jmeter?
If so how?
What should be the ram-up time for this scenario??
解决方案
JMeter's limit of virtual users per Thread Group is very high, to be precise it's 2,147,483,647
The question is: do you have good enough hardware to simulate 10 000 users from a single machine. The process of checking it looks as follows:
Set up monitoring of the CPU, RAM, Network, Swap, Disk usage on JMeter side, it can be done using JMeter PerfMon Plugin
Start with 1 virtual user and gradually increase the load at the same time looking into CPU, RAM, etc. usage. Here there could be 2 options:
you will be able to reach 10 000 users without issues, if this is the case you should be good to go
you will run out of resources earlier, in this case look into i.e. Active Threads Over Time listener to see how many users you were able to simulate from this machine and extrapolate the value to determine how many load generators you will need for 10 000 users using Distributed Testing approach
There is no golden rule for ramp-up time calculation, the good practice is to onboard the users gradually, this way you will be able to correlate increasing load with increasing response time, increasing number of errors, etc. Adding 3 users each second so in 1 hour you will have 10 000 seems a valid starting point to me.